What a rough-in usually includes
- A capped toilet drain in the floor
- A drain for a shower or tub
- A sink drain in the wall or floor
- A vent pipe capped in the ceiling or wall
Making it work
We check that the existing rough-in is where you want fixtures and that the pipes slope correctly. If fixtures need to move, we cut the floor and reroute the drains. Supply lines are run from the nearest main lines, and the vents are tied in. If there is no rough-in, a sewage ejector pump may be needed when the drain is lower than the sewer.
- Locate and confirm existing drains and vents.
- Rework drains as needed.
- Run hot and cold supply lines.
- Pass inspection before walls and floors are finished.
Basement apartments
If the bathroom is part of a second unit, City of Brampton second unit rules apply, including registration and building code requirements. Plan the plumbing and the permit together.
Tools, access and testing
| Tools we bring | Basin wrench, closet auger, cartridge pullers, wax rings |
|---|---|
| What we open | Toilet base, vanity cabinet, shower trim and valve body |
| What we test | Seal at the flange, fill and flush cycles, drips at shut-offs |
Where in Brampton we do this
We take basement bathroom rough-in calls right across the city, including Snelgrove, Heart Lake, Fletcher's Creek South, Bramalea and the streets around them.
Questions we get
How long does a rough-in take?
It depends on how much needs moving. A simple existing rough-in can be ready in a day or two.